College Ave Storm Sewer
Project Description A storm sewer project on College Ave. (south of SW ‘G’ Street) which will install approximately 700 feet of storm sewer and 9 inlets to reduce flooding.
Projected Start Date July 2019
Projected Completion Time 6 weeks
Project Construction Cost $100,911
Wastewater Treatment Plant Sludge Thickening Improvements Project
Project Description This project involves the installation of a Rotary Drum Thickener at the Wastewater Treatment Plant which will be used to thicken waste activated sludge (WAS) before it is sent to the anaerobic digesters to be digested. This will allow more solids to be removed from the plant and disposed of in a more economical manner.
Projected Start Date December 2018
Projected Completion Time October 2019
Project Construction Cost $1,626,117
CSO 006 Sanitary Sewer Improvement
Project Description See link below for more details
Projected Start Date July 2019
Projected Completion Time 7 months
Project Construction Cost $2,290,242
Sewer Rehab and Lining Project
Project Description See link below for more details
Projected Start Date Late April 2019
Projected Completion Time August 2019
Project Construction Cost $348,294
NW 13th Street Interceptor Replacement Project
Project Description See link below for more details
Projected Start Date January 2018
Projected Completion Time December 2019
Project Construction Cost $10,731,236